Projects

    - 35 Plants for the pre-treatment of municipal solid wastes, managing 5,609,847 tonnes.

    - 4 Energy recovery plants, where 1,163,000 tonnes were treated, with an installed electrical power of 101.29 MW.

    - 13 Plants for biomethanization of organic fractions, with a total of 811,359 tonnes managed, with an installed capacity of 39.54 MW and annual production of 103.68 Hm3 of biogas.

    - 39 Composting plants, managing 2,316,028 tonnes.

    - 76 Transfer plant installations in which 3,290,925 tonnes were managed.

    - 31 Packaging treatment facilities, where 338,930 tonnes were treated.

    - 34 Controlled waste dumps, with an annual theoretical dumping capacity of 5,536,376 tonnes.

    - 9 Waste dump degasification installations with an annual average production of 136.79 Hm3 of biogas, with an installed capacity of 38.59 MW.

    - 158 Industrial water purifying stations for 1,190,500 m3 per day for the equivalent of 5,643,700 inhabitants.

    - 19 Sewage operations for the equivalent of 1,385,000 inhabitants.

    - 15 Water supply facilities for 232,000 m3 per day for the equivalent of 915,000 inhabitants.

    - 9 Drinking water treatment plants at 250,000 m3 per day for the equivalent of 293,000 inhabitants.

    - 7 Analysis and monitoring laboratories for the equivalent of 1,423,000 inhabitants.

    - A central laboratory certified under ISO 9001 and accredited to ISO 17025 for potable water, waste water and sludges. This laboratory is accredited as a Collaborating Body for the Water Authority.